*Assemble background information and analyze existing conditions * Research demographic and economic conditions * Map recent development activity * Identify stakeholders * Develop webpage * Contract planning consultant team * Begin community outreach
|
Spring-Summer 2007 |
|
|
Approval of Goals, Concepts, Guidelines and Public Participation Program
|
Fall 2007 |
|
|
|
Plan Formulation |
Spring-Fall 2008 |
|
|
|
Preliminary Master Plan and SMA available for review |
|
|
Joint Public Hearing/Planning Board Adoption |
March 31, 2009/June 25, 2009 |
|
|
|
District Council Worksession to review public hearing testimony |
July 20, 2009 |
|
|
Possible second Public Hearing on amendments and final District Council approval
|