Project Schedule Subregion 6 Master Plan and SMA Schedule with Approved Extension | Community Workshops | May—Aug '08 | Draft Preliminary Plan/SMA | May—Sept '08 | Final Draft Plan Due for Editing/Sign-off | Sept 26, '08 | Planning Board - Permission to Print Preliminary Plan and Public Facilities Consistency Referral | Dec 11, '08 | Joint Public Hearing | Feb 3, '09 | | Council Review of Public Facilities Referral and Approval by Resolution | Feb 17, '09 | Planning Board Worksession on Public Hearing Testimony | Apr 16, '09 | | Planning Board Adopts Plan and Endorses SMA | Apr 30, '09 | | Transmittal to Council | May 11, '09 | | Council Worksession on Adopted Plan/Endorsed SMA | May 19, '09 | | Council Resolution to Approve Plan/SMA (or hold second Joint Public Hearing on Amendments) | May 26, '09 | | Second Joint Public Hearing on Amendments (if needed) | Jun 22, '09 | | Council Worksession | Jul 20, '09 | | Council Approval of Plan/SMA | Sept 9, '09 | |