Project Schedule
|
PLAN DEVELOPMENT PROCESS |
| Planning Board Initiation/GCG-PPP | September 2008 |
| District Council review Initiation/GCG-PPP | October 2008 |
| Plan Development/Plan Writing | Ongoing |
| WSSC/DER/DPW&T Review | March 2009 |
|
APPROVAL PROCESS |
| Permission to print | July 2009 |
| Referral to County Executive and municipalities | September 2009 |
| Joint Public Hearing | November 2009 |
| Request a six-month extension from MDP | February 2010 |
| Planning Board Adoption | March 2010 |
| Transmit adopted plan to District Council, County Executive and municipalities | April 2010 |
| District Council decision to hold additional joint public hearing | June 2010 |
| Second Joint Public Hearing | July 2010 |
| District Council approves the plan (unless they decide to hold a second public hearing.) | October 2010 |
|