Prince George's County Planning Department

Project Schedule

The 18-month schedule planned for this functional master plan is in compliance with CB-39-2005, an ordinance concerning master plan and sector plan procedures.  Following initiation of the PPA Plan in June 2010 by the Prince George's County Planning Board, the County Council reviewed the initiation in July 2010.  After Council approval, the project team conducted public workshops as well as other community outreach events.  Drafting of the plan with goals, policies, and strategies are taking place in the fall and winter 2010.  The draft plan will undergo M-NCPPC review in early 2011 and will be printed in time for a joint public hearing in September 2011.  The process runs through March 2012 or until June 2012 if the District Council sets a second public hearing.


January–June 2010

Planning Board Initiation

June 2010

District Council Authorization

July 2010

Public Participation-Outreach Meetings

August-November 2010

Prepare Plan

September 2010–January 2011

Permission to Print

March 2011

First Joint Public Hearing

June 2011

Planning Board Adoption and Endorsement

September 2011

Plan Transmittal to District Council

September 2011

District Council Takes Action or Sets Second Public Hearing (if required)

November 2011

Second Joint Public Hearing (if required)

January 2012

District Council Approval

February 2012