Project Schedule/Status
Last Updated August 2020
Currently, the project is in the "Construction" phase.
The demolition of the old WSSC facilities was completed in 2009. Construction of the beginner-level bicycle pump track, learning pavilion, picnic area, and playgrounds was completed in 2019. The current construction phase includes an intermediate-level bicycle pump track and a bicycle skills course.
A summary of the project milestones follows:
- Fall 2017 – Summer 2020 – Design and construction of the park
- Summer 2020 – Fall 2020 – Post construction / As-built drawings
- Fall/Winter 2020 – Grand Opening
Actual dates for the completion of the milestones are subject to change dependent upon weather conditions and COVID-19 updates.