Northern Prince George's East West Bikeway Feasibility Study

Northern Prince George's East West Bikeway Feasibility Study


News

Updates

View or download the Northern Prince George’s East-West Bikeway Feasibility Study – Prince George’s County Planning Department here..

Past Public Charrette

A public charrette for the Northern Prince George’s East-West Bikeway Feasibility Study was held on Monday, April 20, from 6:00–8:00 p.m. at the Park and Recreation Administration Auditorium in Riverdale Park, MD. The session provided an opportunity for public review and comment as the County continues work on the 2-mile bikeway feasibility study, which was due on June 30, 2026.

Overview

Project Summary

The Northern Prince George’s East West Bikeway Feasibility Study objective was to review a two-mile segment of a proposed ten-mile bikeway corridor by assessing existing conditions, receiving input from affected public agencies and the public, identifying challenges, developing conceptual designs, and submitting recommendations including possible next steps.

Background

The Prince George’s County Planning Department submitted a Transportation and Land Use Connections grant application to the Metropolitan Washington Council of Governments (MWCOG) to conduct a feasibility study of a proposed ten-mile east west bikeway corridor between Lanham and Lewisdale, in March 2025. This proposal, named the Northern Prince Geroge’s East West Bikeway (NPGEWB), is intended to address a long expressed community desire to construct a bikeway that would provide access between the Washington, Baltimore & Annapolis Trail and three Anacostia River tributary trails. In May 2025, the MWCOG Board of Directors awarded the Planning Department $80,000 in consultant funding to conduct a feasibility study on a two-mile segment of the NPGEWB.

Objectives

Access existing conditions, solicit input from public agencies and the general public, and identify challenges.

Provide conceptual bikeway designs, cost estimates, and recommended next steps.

Timeline
Date Milestone
March 7, 2025 Transportation & Land Use Connections grant application submitted to MWCOG.
May 21, 2025MWCOG Board of Directors awards Planning Department $80,000 for feasibility study.
December 3, 2025Two-mile site visit walk by Planning Department staff, Councilmember Eric Olson and staff, and consultant team.
April 1, 2026 Existing conditions report finalized.

Public agency briefing by consultants.
April 20,2026Public charrette held.
June 30, 2026 NPGEWB Feasibility Study and Appendices submitted.
Area Map

Map

Northern Prince George's East-West Bikeway Study Area Map

Contact Us:

Michael Jackson

Planner Coordinator